BUILD TIMELINE

Pre-Construction:

First Tender:  February 2013
Signed Contracts: 24th April 2013
Council Approval: 27/8
Construction Certificate: 16/9
Job Start: 3/10

Construction:
Day 1: Cut and Fill 3/10
Day 2: Construction fence up 4/10
Day 6: Piering 8/10
Day 7: Plumbing 9/10
Day 13: Forming up and foam pads 15/10
Day 14 - 38:  Frame Complete; Roof Complete; Plumbing Complete
Day 39: Brick started 7/11